User:Sud03r
Revision as of 14:55, 17 June 2010 by Sud03r (talk | contribs) (→Current Tentative GSoC Project Schedule)
sud03r | ||
---|---|---|
Name | Neeraj Kumar | |
Team Member since | 2010-04-26 | |
Working on | Test Framework for scummVM subsystems | |
Personal webpage/BLOG | blog | |
17.neeraj.s@gmail.com |
I am Neeraj, one of the GSoC 2010 students for scummVM.
I shall be working on adding a testing framework for scummVM subsystems.
The objective of this project will be to enhance the ScummVM unit testing infrastructure by implementing a "Test Engine".Unlike unit tests, a test engine would enable testing on all the ScummVM ports.
Using a test-engine would help in testing various features like (game detection, filesystem navigation, graphics, audio.. etc) in an integrated and non-isolated manner.
To track my developments regarding the project, I have created a blog here where I would be posting my updates.
Current Tentative GSoC Project Schedule
Week | Targets | Status |
---|---|---|
24th May - 30th June | Use the quux template to create a dummy engine, refactor it and update on wiki.Use that as basic-testbed. Carve out the design draft of the various subsystems and their details to be tested, design draft can be found here. | Done |
31st May - 7th June | Create the basic generic framework for adding and executing tests and doing non-subsystem specific things like counting and printing results etc. | Done |
8th - 14th June | Use the test framework created in week 2 for adding tests.Write code for the GFXSubsystem tests(Screen Graphics/Overlay/(Palettized/scaled) cursors etc.) | Done (Left some unfinished bit, get back to it next week) |
15th - 21st June | Similarly write tests to test the file subsystem namely (File Accessing and Saving) | In Progress |
22nd - 28th June | Write tests for miscellaneous subsystems namely Timer/event/Date and Mutexes. | Yet to be done |
29th June - 5th July | Tests for Audio Subsystem | Yet to be done |
6th - 13th July | Tests for Midi and audio CD subsystem | Yet to be done |
14th - 20th July | Configure the testing framework to be configurable from a config file, and ability to execute customizable test suites | Yet to be done |
21st - 27th July | Testing of the framework/Documentation | Yet to be done |
28th July - END | Add missing/requested features, improved user interface(if required), Make it as better as it could be ;-) | Yet to be done |
for more details on how each subsystem is tested, please have a look at this. Besides I shall also be posting my progress at my blog.