Line 17: Line 17:
*<strike>June 1: Disassembly framework</strike> Completed May 28
*<strike>June 1: Disassembly framework</strike> Completed May 28
*<strike>June 8: First disassembler (SCUMMv6)</strike> Completed June 4
*<strike>June 8: First disassembler (SCUMMv6)</strike> Completed June 4
*June 21: Generation of code flow graph
*<strike>June 21: Generation of code flow graph</strike> Completed June 14
*June 28: Code flow analysis
*June 28: Code flow analysis
*July 24: Code generation (SCUMMv6)
*July 24: Code generation (SCUMMv6)
*July 29: Second disassembler (KYRA)
*July 29: Second disassembler (KYRA)
*August 6: Code generation (KYRA)
*August 6: Code generation (KYRA)